GENERAL INFORMATION
Client : Turkish Telecom Inc.
Location of Construction |
: |
Acıbadem/İSTANBUL |
Contract Date |
: |
14.12.1990 |
Completion Date |
: |
08.09.1996 |
Contract Value |
: |
18.175.975 US $ |
CHARACTERISTIC FEATURES
Technical Features of Construction :
The construction of Anatolian Side Telecom Office
Building and Acıbadem Guesthouse was started at the
end of 1990. The guesthouse was completed in 1993 while
the office building was completed in 1996.
Total area of construction is 22.000 m2 that includes
A, B and C blocks. The building has a capacity to collect
all telecommunication units which are acting on the
Anatolian side.
Office Building Main Work Items :
Excavation |
: |
52.500 m3 |
Concrete |
: |
13.000 m3 |
Reinforcement |
: |
1.465 tons |
Flat concrete formwork |
: |
46.000 m2 |
Gross formwork |
: |
7.300 m2 |
Aluminum carpentery |
: |
11.000 kg |
Plaster |
: |
33.000 m2 |
Plastic paint |
: |
48.000 m2 |
Alm. facade+reflective glass |
: |
5.830 m2 |
Colored marble covering |
: |
20.000 m2 |
Gypsum board partition wall |
: |
5.350 m2 |
Gypsum suspended ceiling |
: |
2.500 m2 |
Mineral fiber suspended ceiling |
: |
3.000 m2 |
Granite column and wall cover |
: |
1.065 m2 |
Laminated wall cover |
: |
1.550 m2 |
Guesthouse is established by 1 basement, an entrance,
4 floors and a terrace floor. Basement level includes
a laundry room, a dish-washing room, a kitchen, cooling
room, a boiler unit, etc; entrance level has a game/TV
corner, kitchen, and a club room; other floors have
8 suits at each level, total 32 suits; terrace floor
includes, buffet and cafeteria, besides it has three-side
open terrace. 1 panoramic elevator is serving in addition
to 2 normal service elevator.
Guest House Building Main Work Items:
Excavation |
: |
8.500 m3 |
Concrete |
: |
2.000 m3 |
Reinforcement |
: |
290 ton |
Flat concrete formwork |
: |
9.000 m2 |
Aluminum carpentery |
: |
9.300 kg |
Plaster |
: |
11.500 m2 |
Plastic paint |
: |
5.000 m2 |
Colored marble covering |
: |
2.600 m2 |
|