GENERAL INFORMATION
Client : Emirates of Abu Dabi
Location of Construction |
: |
İSTANBUL |
Contract Date |
: |
15.04.1988 |
Completion Date |
: |
15.12.1989 |
Contract Value |
: |
12.776.581 US $ |
CHARACTERISTIC FEATURES
Apart hotel has a special foundation system which was
constructed as a deep piling anchored with mini pile
system.
The finance of the facility was provided by Abu Dabi
found and engineering consultancy was obtained by a
Canadian consultant company.
Main Work Items:
3rd Basement Level |
: |
985 m2 |
2nd Basement Level |
: |
985 m2 |
1st Basement Level |
: |
810 m2 |
Ground Level |
: |
706 m2 |
Floors (10 Floor) |
: |
4.929 m2 |
Total |
: |
8.415 m2 |
|