GENERAL INFORMATION
Client : Marmara University Rectorate
Location of Construction |
: |
İSTANBUL |
Contract Date |
: |
24.07.1985 |
Completion Date |
: |
31.12.1993 |
Contract Value |
: |
8.781.665 US $ |
CHARACTERISTIC FEATURES
The construction was established by 7 no of contracts.
Faculty of Technical Education, Vocational School and
Housing Construction of the Marmara University, Göztepe
Campus
The construction has totally 14.500 m2 closed area.
In the building, there exist the departments of Turning-Levelling,
Electrical, Electronics, Computer, Printing, Metallurgy
and the related ateliers.
Main Work Items
Excavation |
: |
25.000 m3 |
Concrete |
: |
6.200 m3 |
Steel |
: |
850 tons |
Form work |
: |
30.000 m2 |
Brick |
: |
8.200 m2 |
Plaster |
: |
19.500 m2 |
The Guesthouse, Dining Hall and Housing Facilities
Construction of the Marmara University, Göztepe Campus
The construction has totally 3.500 m2 closed area. It
has been completed in two blocks. The 1st block is 750
m2 and is a 3-floored housing facility with 6 flats.
The 2nd block is 2.750 m2 and is an eleven floored building.
The building is used as the guesthouse. On the ground
floor, there exists the dining hall for all faculty
members of the campus. The heat exchanger room, hydrophore
room, laundry and kitchen are all situated at the basement
floor of the guesthouse building.
Main Work Items
Excavation |
: |
1.800 m3 |
Concrete |
: |
800 m3 |
Steel |
: |
96 tons |
Form work |
: |
4.200 m2 |
Plaster |
: |
9.000 m2 |
Vocational School Construction
The construction has totally 13.550 m2 closed area.
In this building, there exist the Vocational Schools
giving education under the Faculty of Technical Education.
Main Work Items
Excavation |
: |
1.100 m3 |
Concrete |
: |
5.100 m3 |
Steel |
: |
680 tons |
Form work |
: |
17.000 m2 |
Brick wall |
: |
6.500 m2 |
Plaster |
: |
27.000 m2 |
Steel framing |
: |
43.000 kg |
Floor covering |
:s |
11.000 m2 |
|